Every Big Push road contract, lot by lot.

The Ministry of Roads and Highways' list of new Big Push awards: 54 contract lots in all 16 of Ghana's regions, GH¢52.59bn in cedi contracts plus the Adawso Bridge (US$497.7m), with the length, contractor and award date of each. Below it, how the government's own figures for the programme compare.

Updated
Format
CSV download, free
Source
Source: Ministry of Roads and Highways, Full List of Big Push Infrastructure Programme (May 2026)
Contract lots
54
53 in cedis, 1 in US dollars
Cedi contract value
GH¢52.59bn
Award values. Plus the Adawso Bridge (US$497.7m)
Length
1,299 km
Across 51 lots; 3 give no length
Regions
16
35 contractors
Chart

The Central Region leads with GH¢12.85bn.

Cedi contract value by region, as the ministry labels each lot, with the number of lots.

Bar chart of Big Push cedi contract value by region, largest first: Central GH¢12.85bn in 5 lots; Western GH¢5.83bn in 2 lots; Volta GH¢5.79bn in 10 lots; Oti GH¢4.67bn in 2 lots; Western North GH¢3.50bn in 5 lots; Greater Accra GH¢3.30bn in 3 lots; Ashanti GH¢3.09bn in 3 lots; Savannah GH¢2.71bn in 5 lots; Northern GH¢2.62bn in 3 lots; Bono GH¢1.99bn in 2 lots; Bono East GH¢1.19bn in 1 lots; North East GH¢1.04bn in 1 lots; Bono/Savannah GH¢0.95bn in 2 lots; Ahafo GH¢0.92bn in 2 lots; Upper West GH¢0.85bn in 3 lots; Eastern GH¢0.48bn in 3 lots plus US$497.7m; Eastern/Volta GH¢0.43bn in 1 lots; Upper East GH¢0.36bn in 1 lots. The table below lists every lot.

GH¢ billion, award values of the cedi contracts. Bono/Savannah and Eastern/Volta are the ministry's own labels for lots that span two regions. The Adawso Bridge (Eastern) is a US dollar contract, marked beside its region's bar and not in it. Source: Ministry of Roads and Highways.
The data

All 54 lots.

In the ministry's order, with its wording. Progress is as the ministry charted it in April 2026.

Download the CSV
Big Push contract lots, Ministry of Roads and Highways list (May 2026): region, project, length, contract sum, contractor, award date and progress as charted in April 2026.
No.RegionProjectAgency, lotLengthkmContract sumAward valueContractorAwardedProgressApr 2026, as charted
1AhafoUpgrading of Bediako Junction - Camp 15 - Sefwi Adabokrom (55km) - Lot 1GHA · Lot 155.00785,083,295.00GH¢Delovely Company Limited15 Sep 2025dates differ0.2%
2AhafoUpgrading of Bediako Junction - Camp 15 - Sefwi Adabokrom (9.5km) - Lot 2GHA · Lot 29.00135,594,474.05GH¢Kingspok Construction Limited15 Sep 2025dates differ25.1%
3AshantiConstruction Of Kumasi Outer Ring Road Project (15km) - Lot 3DUR · Lot 315.001,031,413,200.51GH¢Arab Contractors Ghana Limited24 Nov 2025dates differ3%
4AshantiConstruction Of Kumasi Outer Ring Road Project (15km) - Lot 2DUR · Lot 215.001,029,969,450.51GH¢Arab Contractors Ghana Limited31 Dec 2025dates differ4%
5AshantiConstruction Of Kumasi Outer Ring Road Project (15km) - Lot 1DUR · Lot 115.001,029,969,450.51GH¢Arab Contractors Ghana Limited25 Nov 2025dates differ3%
6BonoConstruction of Sunyani Outer Ring Road (17km) - Lot 2DUR · Lot 217.00997,973,892.11GH¢Kofi Job Company Limited24 Nov 2025dates differ48%
7BonoConstruction of Sunyani Outer Ring Road (17km) - Lot 1DUR · Lot 117.00995,611,392.11GH¢Kofi Job Company Limited24 Nov 2025dates differ36%
8Bono EastRehabilitation of Techiman - Nkonsia - Wenchi Road (32.6km)GHA32.601,186,772,075.23GH¢Volta Impex29 Nov 2024dates differ0.5%
9Bono/SavannahRehabilitation of Wenchi- Sawla Road (Km 0+000 - Km 25+000)GHA · Lot 125.00475,345,120.73GH¢CIWE Ghana Engineering Limited12 Nov 20253.3%
10Bono/SavannahRehabilitation of Wenchi- Sawla Road (Km 25+000 - Km 50+000)GHA · Lot 225.00475,345,120.73GH¢CIWE Ghana Engineering Limited18 Sep 20254.3%
11CentralRehabilitation of Mankessim - Ajumako - Agona Swedru Road and Others Total Length = 111kmGHA111.002,890,514,550.00GH¢E-Speedway Construction Limited30 Dec 202511.6%
12CentralDualisation of Winneba - Cape Coast Road (30 - 54 Km)GHA · Lot 224.001,878,011,148.00GH¢M.A & Constant Company29 Sep 202530%
13CentralDualisation of Winneba - Cape Coast Road (54 - 79 Km)GHA · Lot 325.003,860,486,565.00GH¢M.A & Constant Company29 Sep 202520%
14CentralConstruction of Interchange at Winneba Roundabout (Km 28+200); 10 No. Footbridges; And Dualization into Winneba and Swedru Towns (4.0km)GHA · Lot 1n/a1,117,001,494.70GH¢Mo & Mo Company Limited29 Aug 2025dates differ65%
15CentralDualisation of Cape Coast- Takoradi Road (114 - 139km)GHA · Lot 425.003,104,632,933.00GH¢S&L Construction and Engineering29 Sep 20258.3%
16EasternUpgrading of Akosombo-Gyakiti-Kudikope Feeder Road (KM 8+000 - 31 + 600) and Yeniama Junction -Sedorm Feeder Road (8.40km)DFR32.00333,147,194.00GH¢Mmanab Company Limited21 Nov 202536%
17EasternUpgrading of Apeguso - Mpakadan Feeder Road (9.00Km)DFR9.00145,220,449.36GH¢Build Managers Limited21 Nov 202532%
18EasternConstruction of Adawso BridgeGHAn/a497,664,217.34US$SCL Sonitra Construction Limited30 Dec 20250.2%
19Eastern/VoltaRehabilitation of Atimpoku - Asikuma Junction (0-17.5km)GHA · Lot 117.50433,745,286.43GH¢Ussuya (Gh) Limited18 Sep 202531.5%
20Greater AccraRehabilitation of Tema - Aflao Road (Km 1 - 18.30)GHA17.301,477,093,226.79GH¢First Sky Limited15 Sep 202517.5%
21Greater AccraReconstruction of Dodowa - Afienya-Dawhenya Road (0-24.80km) & Selected Town Roads 3.0kmGHA27.801,116,976,732.05GH¢Oswal Investments Limited15 Sep 202539%
22Greater AccraUpgrading Of Oyibi-Appolonia-Afienya Road (21.0km)GHA21.00708,097,258.50GH¢Proslet17 Dec 20253%
23North EastRehabilitation of Gbintri - Nakpanduri Road (44km)GHA14.001,038,241,891.20GH¢Mawums Limited18 Sep 202525.5%
24NorthernConstruction of 3rd Ring Road, Tamale -Ph. 1 (11km) - Lot 3DUR · Lot 311.00875,018,805.82GH¢Munisco Limited22 Jan 2026dates differ22.7%match: medium
25NorthernConstruction of 3rd Ring Road, Tamale -Ph. 1 (11km) - Lot 2DUR · Lot 211.00873,575,035.81GH¢China Railway No. 5 Engineering Group Limited22 Jan 2026dates differ6.1%match: medium
26NorthernConstruction of 3rd Ring Road, Tamale -Ph. 1 (11km) - Lot 1DUR · Lot 111.00873,575,035.81GH¢Sinohydro Corporation Limited22 Jan 2026dates differ7.8%match: medium
27OtiRehabilitation of Dodo Pepesu - Nkwanta (46.40km)GHA46.40683,902,957.69GH¢Growth 82 Global Ltd.31 Dec 20251%
28OtiConstruction of Dambai BridgeGHAn/a3,989,560,929.14GH¢Maripoma Enterprise Limited29 Sep 20251%
29SavannahRehabilitation of Wenchi - Sawla (Km 125+000 - 150+000)GHA · Lot 625.00448,383,080.79GH¢China Railway No. 5 Engineering Group Limited18 Sep 20252.3%
30SavannahRehabilitation of Wenchi - Sawla (Km 100+000 - 125+000) Including Tinga Town Roads (3km)GHA · Lot 528.00492,409,859.94GH¢China Railway No. 5 Engineering Group Limited18 Sep 20252.7%
31SavannahRehabilitation of Wenchi - Sawla (Km 150+000 - 195+000) and Others (7km)GHA · Lot 745.00861,858,834.26GH¢Maripoma Enterprise Limited18 Sep 20250.2%
32SavannahRehabilitation of Wenchi- Sawla Road (Km 50+000 - Km 75+000)GHA · Lot 325.00423,613,808.58GH¢Poly Changda Overseas Engineering Company Limited29 Sep 20254.0%
33SavannahRehabilitation of Wenchi- Sawla Road (Km 75+000 - Km 100+000) Including Bamboi (3km) And Banda Nkwanta (2km) Town RoadsGHA · Lot 430.00486,405,201.68GH¢Poly Changda Overseas Engineering Company Limited29 Sep 20254.0%
34Upper EastPartial Reconstruction of Navrongo - Tumu Road (27km)GHA27.00360,107,867.58GH¢Medmo Company Limited11 Dec 20250.2%
35Upper WestUpgrading of Tumu - Han - Lawra Road (Km 0 - 10)GHA10.00207,969,054.78GH¢Ghanhali Company Limited17 Dec 20250%match: medium
36Upper WestUpgrading of Tumu - Hamile Road (Km 40.00 - 55.00)GHA15.00207,969,054.78GH¢M.A & Constant Company17 Dec 20250%
37Upper WestRehabilitation of Wa - Han Road (Km 0 - 54)GHA54.00436,384,865.23GH¢Mo & Mo Company Limited17 Dec 20250.2%
38VoltaRehabilitation of Ho - Kpetoe Road (Km 7.70 - Km 27.60)GHA · Lot 519.90976,398,063.10GH¢China Railway No. 5 Engineering Group Limited18 Sep 20252.5%
39VoltaReconstruction of Anyirawasi - Ho Tritrinu (Km 49.4 - 70.0), Ho (Guinness Deport) - Ho Airport 2nd Gate (Km 0-7.7)GHA · Lot 420.601,525,609,304.00GH¢First Sky Limited15 Sep 20259.2%
40VoltaRehabilitation of Penyi - Aflao (Km 85+000 - 107+000)GHA · Lot 922.00537,999,204.14GH¢Medmo Company Limited18 Sep 202561.3%
41VoltaRehabilitation of Kpetoe - Aveafiadenyigba Road (Km 27+600 - Km 51+600) Including Ziope Towns RoadsGHA · Lot 624.00545,928,621.25GH¢Rolider Ghana Limited18 Sep 20258.5%
42VoltaRehabilitation of Kpetoe - Aveafiadenyigba Road (Km 51+600 - Km 62+600) Including Ziope Towns RoadsGHA · Lot 710.90250,302,362.02GH¢Timeline & Innovations Company Ltd.18 Sep 202530.1%
43VoltaRehabiliation of Atimpoku - Asikuma - Ho - Denu - Aflao Road (177Km) Rehabilitation of Asikuma Junction - Anyirawasi (Km 26.0 - 49.4)GHA · Lot 323.40634,061,351.78GH¢Ultra Nexus Limited29 Sep 202513.2%
44VoltaUpgrading of Todome - Toh Kpalime - Dzemeni Feeder Road and Dzemeni Town Road (24.07KM)DFR24.07300,291,294.94GH¢Sanam Ghana Limited17 Sep 202538%
45VoltaRehabilitation of Afiadenyigba - Penyi Road (Km 76.60 - Km 85.0) Including Dualisation of Dzodze Town Road (3.5km)GHA · Lot 8B11.90441,304,080.92GH¢Medmo Company Limited12 Nov 20259.0%
46VoltaRehabilitation of Afiadenyigba - Penyi Road (Km 62.60 - Km 76.60) Including Internal Link Roads Within Dzodze and Penyi Township (3km)GHA · Lot 8A17.00367,904,784.34GH¢Timeline & Innovations Company Ltd.28 Nov 202520.5%
47VoltaRehabilitation of Atimpoku - Asikuma Junction (17.5km - 26Km)GHA · Lot 28.50210,843,969.63GH¢Dwawill Limited29 Sep 202528.8%
48WesternDualisation of Cape Coast- Takoradi Road (139- 164km)GHA · Lot 525.002,509,998,661.00GH¢Alkyro Jules Company Limited29 Sep 20256.9%
49WesternDualisation of Cape Coast- Takoradi Road (164 - 187.6km)GHA · Lot 623.603,323,232,152.00GH¢S&L Construction and Engineering26 Sep 2025dates differ0.7%
50Western NorthUpgrading of Enchi - Kudjouru - Pekyi (Km30.00 - Km 62.00)GHA · Lot 232.00469,040,715.45GH¢Big Aidoo Construction Limited18 Sep 202519%
51Western NorthUpgrading of Adwofua-Oseikojokrom Road Road (Km16-41)GHA25.00390,077,209.00GH¢Cymain Ghana Limited18 Sep 20257%
52Western NorthConstruction of Dadieso - Akontombra Road (Km 4.0 - Km 26.30)GHA22.30816,744,717.14GH¢Kingspok Construction Limited29 Sep 20259.5%
53Western NorthUpgrading of Enchi - Kudjouru - Pekyi (Km 0.00 - Km30.00)GHA · Lot 130.00410,236,050.39GH¢Maripoma Enterprise Limited18 Sep 20250%
54Western NorthConstruction of Enchi - Elubo Road (71.25 Km)GHA71.251,414,219,012.69GH¢Top Engineering International Ltd.29 Sep 20255%
  • Agency: GHA Ghana Highway Authority (trunk roads), DUR Department of Urban Roads, DFR Department of Feeder Roads.
  • Length n/a: the list says Not Applicable (Interchange at Winneba Roundabout, Adawso Bridge and Dambai Bridge).
  • Dates differ: the ministry's released list of sole-sourced contracts gives this lot a different award date (13 lots). The CSV notes give both.
  • Progress: % complete as charted on the Ministry of Roads and Highways Big Push page, April 2026; not audited. Match: medium, the chart row was matched to the lot with medium confidence.
Method

How the data is built.

The table is the Ministry of Roads and Highways' Full List of Big Push Infrastructure Programme, the list of new awards, as uploaded in May 2026; the April upload differs only in one contractor's name. Anansi read the PDF four independent ways, and the reads agree on every lot, amount and date.

Regions, projects and contractors are as the ministry printed them, typos in project names included. Bono/Savannah and Eastern/Volta are the list's labels for lots that span two regions; split, the lots cover all 16 of Ghana's regions.

Contract sums are award values, not spending. 53 lots are in cedis; the Adawso Bridge (US$497.7m) is in US dollars in every version of the list, so it is kept out of the cedi total rather than converted.

The list does not include the 23 projects continued from the previous government, which the ministry publishes separately; they appear in the comparison of official figures below.

Progress percentages are the ministry's, from the charts on its Big Push page for April 2026, matched to lots by name and chainage. They are not audited, and later reports may differ.

Sources

  1. 1

    Ministry of Roads and Highways · 7 May 2026

    Full List of Big Push Infrastructure Programme
  2. 2
  3. 3

    Ministry of Roads and Highways · 31 Mar 2026

    Full List of On-Going Big Push Infrastructure
  4. 4
  5. 5
  6. 6

    Office of the President · 27 Feb 2026

    State of the Nation Address 2026, p. 17
The money

What the Budget and the Mid-Year Review say.

The contract sums above are award values. For money allocated and spent, the government's own documents give these figures, each quoted with its label.

Official figures

How the official figures differ.

Government statements count the programme in different ways, and set against the ministry's published lists they do not all reconcile. Each statement below keeps its source; where documents differ, the page says so without guessing why.

  • New projects50 projects, 1,144 kmThe State of the Nation Address put new works at 50 projects, 1,144 km and GH¢50bn. The ministry's list has 54 lots, 1,299.02 km and GH¢52.59bn plus a US dollar contract, and its own page says both "50 projects" and "54 New Awards". The 1,144 km cannot be rebuilt from the list.Office of the President, State of the Nation Address 2026, p. 17, 27 Feb 2026
  • All projects73, 77 or 8773 (State of the Nation Address) is 50 new plus 23 inherited; 77 (ministry page, May 2026) is the 54 lots plus 23 inherited. The Mid-Year Review's 87 includes 10 urban and 3 feeder roads, exactly as many as the two lists hold, so its extra projects are trunk-road contracts in neither published list.Ministry of Finance, 2026 Mid-Year Fiscal Policy Review, paras 563 and 564, p. 66, 23 Jul 2026
  • Contracts awardedGH¢63bnThe 2026 Budget put road contracts awarded so far at GH¢63bn, and the Roads Minister repeated the figure in March 2026. Lots on the list dated on or before 13 November 2025 total GH¢38.54bn; every cedi contract on both lists totals GH¢62.21bn before the dollar and euro contracts. The figure cannot be reproduced from the lists.Ministry of Finance, 2026 Budget Statement and Economic Policy, para 1183, p. 145, 13 Nov 2025
  • LengthNearly 2,000 kmThe State of the Nation Address said nearly 2,000 km; the Roads Minister said over 1,700 km on 24 March 2026. The two lists add up to 1,950.40 km, or 1,890.40 km without two inherited lots that repeat a road's full length.Office of the President, State of the Nation Address 2026, p. 17, 27 Feb 2026
  • Award dates2 lots dated before the launchThe programme was launched on 16 September 2025. Lot 8 (Techiman - Nkonsia - Wenchi Road) is dated 29 November 2024 and Lot 14 (Interchange at Winneba Roundabout) is dated 29 August 2025 in every version of the list; the ministry's released list of sole-sourced contracts dates them 29 November 2025 and 29 September 2025. In all, 13 lots carry different dates in the two documents, which may record different events, such as approval and signature; neither says.Daily Graphic, Mahama cuts sod in Afienya to start Big Push, 16 Sep 2025
Download

Get the full dataset.

The CSV has every lot in the table, with the notes behind each one.

  • 54 contract lots: region, agency, project, lot, length, contract sum and currency, contractor and award date
  • The contractor name and award date exactly as printed, beside the cleaned versions
  • A note on every lot where ministry documents differ: dates, amounts, names and lengths
  • Progress as charted by the ministry for March and April 2026, with the match confidence

ghana-big-push-roads.csv · One row per lot · Free · Updated 18 Oct 2026

We record your email and the dataset you asked for. See the privacy policy.

FAQ

Questions about this data.

Request a demo

Check the official figures yourself, with the sources.

Anansi holds the 2026 Budget, the 2026 Mid-Year Review and the national press, and answers questions across them with their sources cited. Tell us who you are and we will set up a demo on your own questions.

  • 01A demo on the questions your team is working on now
  • 02A scoped pilot for your team
  • 03A proposal sized to your seats and coverage

Prefer to talk it through first?

Talk to sales